From the Dean's Desk


Guest Column: Ron Grisoli

Ron Grisoli

Ron Grisoli

Monday, 12 May 2025

Summer Construction Updates

Under the leadership and vision of Dean Cremers, we are embarking on a bold expansion of our facilities and resources to advance the College's strategic priorities. Building the Good in Business: A New Era of Business Education at Notre Dame is an initiative comprising a series of construction projects to support the College’s mission as a leading business school guided by the University’s Catholic identity.

You may already have heard the “sounds of progress” as several construction projects are currently underway. As summer approaches, more initiatives will begin, bringing the total to 10 active construction projects. These projects will touch nearly every part of the building, from the roof and exterior masonry to multiple interior spaces. This marks the most significant construction effort at Mendoza since its original opening in 1996.

Given the scope and scale of the work planned for this summer and beyond, some disruptions will be unavoidable. We are working closely with contractors to minimize the impact, but factors such as weather and supply chain issues may affect timelines. As a result, we may not always be able to provide advance notice for all disruptions. For regular updates, please visit the Mendoza Exchange website. Urgent updates and alerts will be communicated via email.

For detailed information on logistics and affected areas, please refer to the MCoB Construction Logistics plan.

 

Overlay of construction projects on an aerial photo of Mendoza College of Business.

 

Project Highlights & Updates

Following is an overview of the active projects:

BEHAVIORAL LAB
Status: On Schedule
Expected Completion: June 2, 2025 (Move-in date)

  • Final stage underway: technology and furniture installations in progress

 

NORTH ADDITION
Status: On Schedule
Expected Completion: August 2026

  • Current Work:
    • Concrete footings and retaining walls to be completed by the end of June.
    • Dean’s suite support staff to be relocated from June 1, 2025, through June 9, 2026, to allow exterior wall connection.
  • Next Steps:
    • Structural steel assembly: July–August
    • Basement Foundation Cutting: May 19 – June 30 (Disruptive at times)
      • Six openings to be cut into foundation walls to access the addition’s basement mechanical area
      • Temporary barriers will contain slurry from wet concrete saws
      • Classrooms L003, L014, L050, and L051 offline from June 5–30
    • Slab Pour: June 25–26
  • Structural Steel & Decking: June 30 – August 13

 

JORDAN AUDITORIUM VIDEO WALL
Status: On Schedule
Expected Completion: August 18, 2025

  • Support structure complete; DLED component installation begins May 19
  • Calibration scheduled through August 18
  • Auditorium will reopen in time for fall semester

 

132 SUITE RENOVATION
Status: Completed (Punch List Pending)
Completion Date: May 5, 2025

  • Marketing & Brand Strategy Team moved in on schedule
  • Minor remaining punch-list items being addressed

 

TRADING ROOM
Status: On Schedule
Expected Completion: August 18, 2025

  • Demolition began May 5
  • Temporary construction walls to be installed in atrium post-commencement

 

BUSINESS LIBRARY RELOCATION
Status: Planning
Expected Completion: August 2025

  • Finalizing construction documents
  • Cost estimation and scheduling underway

 

CLASSROOM FINISHES REFRESH
Status: Scheduled
Expected Completion: August 22, 2025

  • Includes new lighting, carpet, paint, and updated horseshoe tables
  • Phases:
    • Group 1 (May 12 – June 29): Classrooms 160 & 161
    • Group 2 (June 30 – August 22): Classrooms 122 & 133
  • Additional classrooms will be refreshed over the next 2–3 years

 

MENDOZA RESTROOM RENOVATIONS
Status: Scheduled
Phased Completion:

    • Group 1 (May 19 – August 15): Lower Level & 2nd Floor
    • Group 2 (Summer 2026): Floors 1 & 3

  • Updates include new fixtures, tile, lighting, and partitions

 

MENDOZA ROOF PROJECT
Status: Scheduled
Expected Completion: October 31, 2025

  • Replacing flat roof membrane, installing green roof features, irrigation, and safety systems
  • Slate roof repairs included
  • The majority of the work is to be completed by August 30; plant and irrigation installation through October 31
  • Sequenced to ensure the courtyard remains usable during home football weekends

See full details: Mendoza Sequence Roof Plan & Logistics.pdf

 

MENDOZA MASONRY REPAIRS
Status: Scheduled
Expected Completion: October 31, 2025

  • Includes brick repair/replacement, cleaning, and sealing around the entire exterior of the building.

 

We’re thrilled about the new and enhanced spaces and amenities these projects will bring to our students. At the same time, we understand that ongoing construction may affect your daily routine, and we’re doing everything we can to minimize the disruption. Your patience and understanding are truly appreciated as we continue Building the Good in Business.

In Notre Dame,

Ron 

Ron Grisoli
Facilities Program Director
Facilities & Program Operations

Read More

Got news to share?  Let us know!

Construction Updates

Mendoza Facilities


Building the Good in Business

A lot is happening around the Mendoza building! Ron Grisoli will write a column for the May 12 Mendoza Exchange with more details about the construction activities scheduled for this summer. Here are few updates for this week and next:

  • The Marketing & Brand Strategy team is now moved to the team’s new offices in Mendoza 132.
  • Preparation has begun for the construction of the Trading Room in Mendoza 123.
  • Restrooms on the lower level and second floor will be closed this summer with demolition starting on May 19.
  • Work on Mendoza’s roof will start May 12 with the removal of the rocks on the flat-roof areas. The work will pause for the commencement weekend. It’s likely to be noisy!
  • Renovations to Mendoza classrooms begin May 12. Phase 1 includes rooms 160 and 161. New tables, lighting and carpeting will be installed, and the rooms will be repainted.

 

Concrete Saw Cutting in Mendoza’s Basement

Beginning May 19, preparations will start to cut six new door openings through the existing concrete foundation walls in the lower level of Mendoza. These openings will connect the current basement to the basement of the North Addition. This work is scheduled to continue through June 30.

 

Each opening requires several days of preparation followed by a full day of concrete saw cutting. Please be advised that this process will generate significant noise, which may be heard throughout the building. The greatest impact will be on the north end of the basement.

 

To reduce disruption, classrooms in the basement and on the first floor of the north side of the building will be closed from June 5 to June 30. The affected classrooms include: L003, L014, L050, L051, 121 and 122.

 

Additional updates will be provided regarding any office spaces that may be affected during this work.

 

Please email questions or concerns to mendoza-fixit-list@nd.edu.

January 13, 2025

MCOB Updates


Wall Street Journal Subscription Update

Collections Update from the Mahaffey Business Library

We now have direct access to the Wall Street Journal

If you are already personally subscribed to the Wall Street Journal already. Do 2 things:
1. Cancel your current subscription
Please email AcademicSupport@dowjones.com or call 1-800-JOURNAL to cancel. When
requesting an account cancellation, indicate that your University has partnered with WSJ to
provide complimentary memberships to students, faculty, and staff.

2. Go to WSJ.com/ND and do a one-time account creation.

If you are not personally subscribed to the Wall Street Journal. Do 1 thing:
1. Go to WSJ.com/ND and do a one-time account creation

Our Capital IQ access policy has changed and can now be accessed by the following methods.
1. Access Capital IQ at the following link with your netID and password.
2. Alternatively, access as a clickable icon in okta.nd.ed

Please reach out to Ask a Business Librarian if the sign-in gives you an error or the Okta icon does not
appear

Accounts from the previous policy will still work for a brief migration grace period. Eventually, these
accounts will become inaccessible requiring all users to access via the new policy. Our Business Library Databases Page also maintains active links to each of these resources in addition to many others.

October 10, 2022

Mendoza IT

Tech Tips


Google Scholar

Citation analysis is being monitored more in the academic profession as a measure of impact. By creating a Google Scholar Profile (leave it public, which is the default) you can increase the accessibility of your research and have immediate access to h-statistics and other impact metrics.

February 3, 2020

ND Google Shortcuts

Did you know there are shortcuts to log in to your ND Gmail and other Google services? If you visit google.nd.edu you are taken directly to Google Drive, or to the login page if you are not already logged in. You can also skip logging in to insideND or visiting gmail.com by going directly to gmail.nd.edu for Gmail. You can also go directly to Google Calendar by visiting gcalendar.nd.edu.

February 3, 2020

Manage When Participants Join Zoom

If you enable Waiting Room in your Zoom settings, you can manage when new attendees are able to join a meeting from the list of Participants. When these tools are enabled, the option to allow attendees to join the meeting before the host arrives is automatically disabled.

February 3, 2020

Window Snapping

In Windows, you can drag a window to the left or right edge of your screen to make it fill one half of the screen, or drag to the top of the screen to maximize the window. View two windows side by side quickly and easily. You can also press the Windows key + left or right arrow to make the active window fill the left or right side of the screen.


Minimize All Windows

Sometimes you have a bunch of applications running, and you want it all to go away so you can get to the desktop. Simply pressing Windows key + D will minimize everything you have up, which will save you some time pressing the minimize button for each window. To bring everything back, press the Windows key + D again to restore your windows.